Ribbonwood Farm
Avon Construction have successfully completed the excavation and installation of a brand new filtration sewage treatment plant for a residential estate in Anderson, Dorset. Work commenced in early September and completed at the beginning of October, resulting in a 4 week timescale for the project.
This project came with many challenges such as, having to maintain constant access for the residents to the estate throughout the day whilst delivering progress with the work on site and piling sheets 4.3m into the ground near the boundary of a neighbouring house.