Trowbridge Station Link
Work has finished at Trowbridge for the reconstruction of an old timber retaining wall with a new concrete filled bag wall. Contracted by Sustrans and acting as principal contactor, we were employed to demolish the old retaining wall and build a new wall in its footprint alongside a railway embankment.
The project scope of works included vegetation clearance, full demolition of existing retaining wall, installation of new concrete filled bagged retaining wall inclusive of drainage weep holes for water management, footpath constructions, handrail installation and surfacing works including full depth construction and overlay. Works were undertaken in phases to ensure continued slope stability throughout the project. Site works commenced in October of 2024 and were successfully completed in March 2025.